How to make a construction schedule
Turn a scope of work into a construction schedule with phases, dependencies, planned labour and a baseline you can track.
Break the job into phases
For a bathroom renovation, start with preparation, installation and finishing. Give each task an observable outcome, such as removing the fixtures or setting the tile. Add a milestone for handover.
Link the work that depends on other tasks
Painting may need to wait until the drywall joints are finished. Ordering fixtures can run in parallel. A phase groups related work. A dependency line between two bars tells you which job comes first.
Separate labour hours from duration
A job can span three calendar days and require 24 hours of labour in total. Enter planned hours and crew size separately. On site, record the hours worked and the number of days the job actually took.
Save the original plan
Once dates are agreed, save a baseline. If a delivery pushes plumbing back two days, adjust the task and compare its new finish with the agreed date. Then check the tasks that depend on it.
Share the next step
Open the read-only preview before sending the client their link. Check the next milestone and choose whether labour hours and crew sizes should be visible.